In the current offshore market, flexibility is essential. Projects can be delayed or fast tracked at short notice. We recently supported our client with the quick turnaround mobilisation of a trencher with a-frame, winch and ancillary equipment, from Montrose to Cyprus.

• Project notification on Friday…
• Vessel confirmation and design clarification on Tuesday…
• Onboard installation support on Friday…
• Vessel departed on time Friday pm.

There were some long hours and late nights and by leveraging the time differences and with seamless cooperation between our UK engineers and our US team, Tymor produced an expedited seafastening material list, a complete mobilisation drawing package, design calculations and a verification report – all fast tracked to match the client’s schedule. Even those last minute equipment changes and additions were facilitated because we were onboard to make those design changes.